27. Deferred revenue

  As at Dec 31 2014 As at Dec 31 2013
Non-current    
Non-depreciable portion of the value of gas service lines financed by gas buyers  337  387
Connection charge  382  403
Grants  843  740
Other deferred revenue  19  3
Total non-current  1,581  1,533
     
Current    
Non-depreciable portion of the value of gas service lines financed by gas buyers  48  48
Connection charge  19  19
Other deferred revenue  160  119
Total current  227  186
 

Grants

The Group implements projects for which EU co-financing has been obtained. The largest projects are carried out by the Parent and involve extension of the gas storage capacities.

In 2014, the Parent received grants to finance the following projects:

  • “Wierzchowice Underground Storage Facility” – PLN 46.6m (2013: PLN 31.9m),
  • “Kosakowo Underground Storage Facility” – PLN 6.5m (2013: PLN 49.9m),
  • “Husów Underground Gas Storage Facility” – PLN 6m (2013: PLN 17.8m);
  • “LNG-based conversion of Ełk and Olecko from propane-butane to E-gas” – PLN 3.6m.

The grant amounts are recognised as Deferred revenue and will be released to operating income gradually in proportion to the depreciation charges on the tangible assets financed.